Teri developed a PERT chart that showed her the longest line of activities where a delay in any of the activities would cause a delay in her entire project. Teri was using the _____ method.
activity path
critical path
longest path
Gantt path
The post Teri developed a PERT chart that showed her the longest line of activities where a delay in any of the activities would cause a delay in her entire… first appeared on myassignmentwriters.org .
Teri developed a PERT chart that showed her the longest line of activities where a delay in any of the activities would cause a delay in her entire… was first posted on August 28, 2023 at 8:52 pm.