project mgmt 1 – My Nursing Experts

project mgmt 1 – My Nursing Experts

1. Should a project manager manage critical path tasks differently than noncritical path tasks? What is the impact to to the project?
2. Please complete the following for the table of information:

Draw the network diagram.
List the network path(s).
Determine the critical path(s).
Determine the float for each activity.

Smart Draw (Links to an external site.) provides Drawing tools in Word, Visio, or Powerpoint and can also be used for creating the diagram.

Activity

Duration

Dependency

Float

Start

0 days

A

5 days

Start

B

2 days

Start

C

3 days

A, B

D

5 days

Start

E

6 days

Start

F

4 days

D, E

G

2 days

C, F

H

5 days

G

I

7 days

G

J

3 days

H

Finish

0 days

I, J

3. The next step is to actually create the project schedule. (Check attached file) . You will do this by entering the tasks and durations, outlining any dependencies to ensure the full timeline is developed. You can use SmartSheet or Excel to create a project schedule.
 
Do you need a similar assignment done for you from scratch? We have qualified writers to help you. We assure you an A+ quality paper that is free from plagiarism. Order now for an Amazing Discount!Use Discount Code “Newclient” for a 15% Discount!NB: We do not resell papers. Upon ordering, we do an original paper exclusively for you.

Rate this post
"Do you need a similar assignment done for you from scratch? We have qualified writers to help you with a guaranteed plagiarism-free A+ quality paper. Discount Code: SUPER50!"